Lagos-Calabar highway sections to open by December, Umahi says, as he woos Igbo voters in Lagos

File photo. Photo: Engineer Abdullah / Pexels

Works Minister Dave Umahi says the Federal Government plans to inaugurate Sections One and Two of the Lagos-Calabar Coastal Highway, without their bridges, in November or December. He used an inspection of the project in Lagos on Sunday, November 22, to ask Igbo residents of the state to back the All Progressives Congress (APC) and President Bola Tinubu.

Umahi said the contractor, Hitech Construction Company, had completed more than 200km of the road in two and a half years, according to a News Agency of Nigeria report carried by Peoples Gazette. The Controller of Works in Lagos, Olufemi Dare, said there are 20 bridges across the two sections, ten on each. One is finished, and work is going on at all the others at the same time.

Hitech’s managing director, Dany Abboud, said about 85 per cent of the piling for the bridges was done and road construction on Section Two was complete, Freedom Online reported. He said road furniture should be finished before the end of December, leaving the bridges outstanding. The progress figures came from the ministry and the contractor and have not been independently verified.

Turning to politics, Umahi urged Igbo people living in Lagos, particularly those from the South-East, to support the APC government in the state and Tinubu’s re-election bid. He said Tinubu had supported South-Easterners and appointed many of them while he was governor of Lagos, and told them to "do in Rome as the Romans do." He said he was confident Tinubu would win in January 2027. No response from opposition parties was included in the reports.

The 750km highway begins at Ahmadu Bello Way, Victoria Island, and is planned to run through Ogun, Ondo, Delta, Bayelsa and other states to Cross River. Umahi temporarily opened a 47.47km stretch of Section One on December 12, 2025, while work continued, Peoples Gazette reported at the time. Abboud said then that the 106km of Sections One and Two would be completed by December 2026. A month earlier, Umahi had set April 2026 for completing Section One and half of Section Two for full commissioning, BusinessDay reported.

No exact date for the inauguration has been announced, and the bridges on both sections will still be under construction after the planned opening.

Source: Peoples Gazette, Freedom Online, Peoples Gazette (2025), BusinessDay