Civic & Governance Featured

The Power Plant Next Door: What Victoria Island’s New Grid Means for the Balogun Family, and for the Rest of Lagos

Explainer · Power

The Power Plant Next Door: What Victoria Island’s New Grid Means for the Balogun Family, and for the Rest of Lagos

A 40MW private power network is coming to Victoria Island. It will change how Cynthia Balogun’s bank keeps its lights on. Whether it reaches her own home a few streets away, or the homes of the people who work for her family, is another matter.

40MWPhase 1 capacity of Victoria Island Power
12.6kmUnderground feeder network
3,000+Diesel generators reportedly running on VI
200MWPower reaching Lagos but not its consumers

Meet the Baloguns*

  • Jide BalogunOil and gas executive, office on Victoria Island
  • Cynthia BalogunBanker at a Victoria Island headquarters
  • Their three childrenStudying abroad; they hear the generator on every video call
  • HomeA family compound on Victoria Island, on the grid and a diesel generator
*An illustrative, fictional family. See the editor’s note at the end.

Two kinds of power, one island

At 7.40 on a weekday morning, Cynthia Balogun’s car pulls out of the family’s compound on Victoria Island. Ten minutes later it turns into the forecourt of her bank’s headquarters. The building hums. Behind it, a bank of diesel generators is doing what the national grid could not.

Her husband Jide, an oil and gas executive, is already at his desk a few streets away. His first meeting is about gas supply: the fuel his industry sells, and the fuel whose shortages regularly dim the national grid.

At home, the house has just switched from grid supply to generator for the second time this morning. The Baloguns’ three children are studying abroad, and it is the hum of that generator they hear about most on family video calls, usually when a call drops at the switchover.

The couple’s driver will spend the day waiting beside that office generator. Tonight he goes home to the mainland, where the grid is weaker still, and where there may be no generator at all.

From December, or perhaps early 2027, Cynthia’s bank may run on something new. Whether the Balogun home, or the driver’s, will is far less certain.

What is being built

The Lagos State Electricity Regulatory Commission (LASERC) has licensed Elektron Energy Development Strategies Limited to generate electricity in the state. Its flagship project, Victoria Island Power (VIPL), is a 40-megawatt gas-fired plant being built with Eko Power, formerly EKEDC. It is designed to grow to 70MW. The power will reach customers through a 12.6-kilometre underground feeder network.

This is “embedded” power: generated on the Island, used on the Island, and never passing through the national grid, whose collapses regularly plunge the country into darkness.

How power reaches you: the grid route vs the embedded route

THE NATIONAL GRID ROUTE Power stations (far from Lagos) TCN transmission (Akangba, Ijora…) BOTTLENECK ~200MW can’t get through to DisCos Homes & shops (incl. the mainland) Losses, tripping, vandalism and weak distribution lines sit between the plant and the consumer. THE EMBEDDED ROUTE (VIPL) VIPL gas plant 40MW, on Victoria Island Gas via NGML 12.6km underground feeders under Eko Power’s licence 150+ target customers Banks, hotels, telecoms, multinational offices Grid stays connected as backup: the “power island” model THE NATIONAL GRID ROUTE Power stations, far from Lagos TCN transmission (Akangba, Ijora) BOTTLENECK ~200MW can’t get through to DisCos Homes and shops, incl. the mainland THE EMBEDDED ROUTE (VIPL) VIPL gas plant 40MW on Victoria Island · gas via NGML 12.6km underground feeders, Eko Power licence 150+ target customers Banks, hotels, telecoms, offices Grid stays connected as backup: the “power island” model
Simplified illustration. Sources: Elektron Energy, BusinessDay, LASERC via Nairametrics, Tetracore.

The start date is not settled. Elektron told BusinessDay it is firmly on track for commissioning in December 2026. But ThisDay’s report of the company’s own customer event put completion in the first quarter of 2027. The project has also grown and slipped along the way. It was first announced as a 30MW plant, due for completion in the first quarter of 2026.

The projectAs first plannedAs of September 2026
Capacity30MW40MW, scalable to 70MW
EnginesThree Wärtsilä 34SG gas sets, with room for a fourthWärtsilä 34SG gas sets, installed on site
CompletionQ1 2026December 2026 (Elektron) or Q1 2027 (ThisDay)
InvestmentAbout $50–51 millionNo updated figure published
RegulatorFederal (NERC) eraLASERC generation licence, September 2026

Why Cynthia’s bank wants in

Victoria Island runs on diesel. Elektron says more than 3,000 commercial diesel generators reportedly operate there, and that self-generation on diesel can cost as much as ₦600 per kWh. Elektron expects most connected businesses to save up to 40 per cent. But the tariff is still subject to final commercial agreements, so that figure is a promise, not a price.

The customers Elektron is courting are institutions like Cynthia’s: bank headquarters, hospitality companies, telecommunications facilities and multinational offices. It is targeting over 150 of them.

The savings claim has moved: three figures, three baselines

InfraCredit project profile (vs grid-based supply)up to 20%
Elektron website (company-wide power cost savings)34%
Elektron executive, Sept 2026 (vs diesel-heavy energy mix)up to 40%
These figures use different comparisons and are not directly comparable. No VIPL tariff has been published; prices are set in private power purchase agreements.
“Victoria Island Power changes that equation.”Ayomide Oladapo, Executive Director, Business Development, Elektron Energy (ThisDay)

Can the Baloguns connect their home?

Possibly, but nobody is promising it. InfraCredit, one of the project’s financiers, describes VIPL as serving both commercial and residential customers in Victoria Island. Elektron’s chief executive has listed high-end residential complexes among the Island’s occupants the plant is meant to serve. Yet every recent announcement, from the licence to the customer day, speaks only of businesses.

For now, a household like the Baloguns’ sits inside the plant’s footprint without any clear route onto its network. The family can afford private power; they may simply not be the customer VIPL is built for.

How the deal works

VIPL sells to customers on a willing-buyer, willing-seller basis. Its financiers are frank about the strategy: InfraCredit describes the savings as coming from migrating “quality customers” off the grid onto the plant as their main supply.

Eko Power is not the loser it might seem. Elektron’s chief executive says distribution companies earn wheeling charges from such arrangements, and in some cases take equity stakes. And connected businesses keep the grid as a backup. Elektron’s chief executive calls these “power islands”, able to run independently of the national grid while remaining connected to it. It is an insurance policy that neither the Balogun home nor the driver’s household has.

Jide’s question: where does the gas come from?

Jide would ask this first. VIPL’s gas is supplied through a partnership with NNPC Gas Marketing Limited (NGML). That is a reassuring name, but no guarantee. National gas shortages forced Eko to downgrade several Band A areas in February. A gas-fired plant on Victoria Island draws on the same national gas system that failed those customers.

The driver’s house: what changes?

Directly, nothing. VIPL was not built for homes in Mushin, Ajegunle or Ikorodu. Even Eko Disco’s chairman, at the 2023 groundbreaking, spoke of residents of Victoria Island and its environs, not the city at large.

The bigger problem for the driver’s street lies elsewhere. This month, LASERC investigated reports that about 200 megawatts of electricity could not reach consumers in Lagos. It found that both TCN and the DisCos had enough capacity, but bottlenecks between the two were blocking the flow. It blamed weak distribution infrastructure and system protection, vandalism and cable theft, and frequent tripping in the rainy season.

The power Lagos is losing vs the power VIPL will add

Power stuck between TCN and the DisCos (LASERC, Sept 2026)~200MW
VIPL at full build-out70MW
VIPL Phase 140MW
The stranded power is roughly five times VIPL’s Phase 1 output. Sources: LASERC via Nairametrics; Elektron Energy.
“There are a few bottlenecks between the two companies that need to be addressed.”Engr. Adekunle Olapade, LASERC Executive Member, Engineering and Standards (Nairametrics)

For the driver’s household on the mainland, and for millions like it, clearing that bottleneck would do more than any number of Victoria Island power plants.

Eko Power has not said whether the grid supply its VIPL customers stop using will be redirected to other feeders. That is the question Lagosians should keep asking.

The people in the Baloguns’ orbit

The driver, the security men at the bank’s gate, the food vendors and the cleaners spend long hours beside generator exhausts. They may gain the most from VIPL, even though they will never sign one of its contracts.

Research at the University of Lagos linked high pollution readings in Yaba’s residential areas to exhaust from diesel and petrol generators. Diesel generator exhaust carries more than 40 toxic air contaminants, including known or suspected carcinogens such as benzene and formaldehyde. If even part of Victoria Island’s generator fleet falls silent, the people who work in its fumes breathe easier. No one, however, has published air-quality measurements for the district to prove it.

There are losers too. Diesel suppliers, tanker drivers and generator mechanics who service the Island’s businesses could see their work shrink.

WhoWhat VIPL changesVerdict
Cynthia’s bankDedicated supply, claimed savings of up to 40%, grid kept as backupGains
The Balogun homeInside the footprint, but no clear route for households yetUncertain
The driver’s mainland homeNo direct change; the real issue is the 200MW bottleneckUnchanged
Gatemen, vendors, cleaners on VILess generator smoke and noise, if generators are retiredLikely gains
Diesel suppliers, generator mechanicsLess work on the IslandLose
Eko PowerLoses top grid customers, earns wheeling chargesMixed
LASERCA flagship test of its new licensing regimeGains, if delivered

The bigger picture: a test case for the mainland

VIPL matters to the driver’s household not for what it powers but for what it proves. Since Lagos took over regulation of its own electricity market from the federal regulator, becoming the eighth state to do so, LASERC has begun licensing private operators to generate and distribute power closer to users.

Some licences reach beyond the Island:

  • Isolo: Isolo Power Gen Limited has approval for a 9MW embedded plant along the Apapa-Oshodi Expressway, with a separate company licensed to distribute its power locally.
  • Ayobo-Ipaja: Enaro Energy Mini-Grid Limited is approved to run mini-grids in Ishokan Phase 1 and Mercyland Phase 1.
  • Coming up: About 40 more applications await approval across embedded generation, captive power and mini-grids.

How we got here

  1. 2015Eko Disco begins talks on embedded generation for Victoria Island.
  2. April 2018Victoria Island Power Ltd is incorporated as Elektron’s project company.
  3. July 2023Groundbreaking: a 30MW plant, costed at about $50 million.
  4. Q4 2024Wärtsilä books the equipment contract for three gas engine sets.
  5. December 2024NERC transfers regulation of the Lagos electricity market to LASERC.
  6. March 2026Governor Sanwo-Olu inaugurates the LASERC board.
  7. May 2026LASERC approves 14 licences and promises 24-hour franchise zones.
  8. 27 August 2026Elektron shows the 40MW plant to prospective customers.
  9. September 2026LASERC grants Elektron a generation licence, then flags the 200MW bottleneck.
  10. October 2026 (due)First 24-hour franchise zones and metering pilot.
  11. December 2026 or Q1 2027 (due)VIPL commissioning, depending on whose date you trust.

LASERC has also made promises that would reach ordinary households directly. The franchise zones matter most. As of May their locations had not been disclosed, and with October a week away, they still have not been named.

LASERC promise (May 2026)DueStatus
Two or three 24-hour electricity franchise zonesOctober 2026Not yet named
100% metering initiativeFrom July 2026No public progress update found
Consumer complaint centres: Amuwo Odofin, then Ikorodu and EpeAugust–September 2026Opening not confirmed in reports found
Draft Lagos electricity market rulesOctober 2026Pending
Electric Eye of Lagos metering pilotOctober 2026Pending

The risks

GasThe same national gas system that dims the grid supplies this plant.
Tariff opacityPrices are set in private contracts, not published tariffs.
A two-tier cityCynthia’s office could be lit round the clock while her driver’s street waits for the grid to recover.

Questions Lagosians should be asking

  1. Eko Power: Where does the grid power freed up by VIPL customers go?
  2. LASERC: Which areas become the 24-hour franchise zones, and when?
  3. Elektron: Can households on Victoria Island connect, and at what tariff?
  4. TCN and the DisCos: Who fixes the 200MW bottleneck, and by when?
  5. Everyone: What happens to VIPL’s supply when national gas runs short?

The bottom line

When the Balogun children next fly home, their mother’s office may finally be free of the generator hum. Their family home, a few streets away, may not. And the driver who collects them from the airport will go home to the same grid he has always known.

VIPL shows that Lagos can attract private money to build working power infrastructure under its own regulator. Whether that success travels beyond the Island’s commercial core depends on LASERC keeping its promises to ordinary consumers, and on Lagosians holding it to them.

Editor’s note: The Balogun family is a fictional composite, created to show how this project touches different parts of Lagos life. All facts about the project, the regulator and the power sector are drawn from published sources.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.