MoU, Not Water Yet: What Lagos’s Lekki Pipeline Deal Really Means

By Nkanu Egbe

2,455 Million litres a day — Lagos-wide demand
955 Million litres a day — installed supply
1 Year MoU duration

If you live in Lekki or Ajah, the ritual is familiar. A borehole that runs orange in the dry season. A tanker driver’s number saved under “Water Guy” in your phone. A sachet or bottle bought not as a luxury but as insurance. So when news broke that the Lagos State Government had signed a Memorandum of Understanding to run a pipeline under the lagoon and into the Lekki Concession Area, the instinct among residents was equal parts hope and déjà vu.

But before asking what’s different about this deal, it’s worth asking a more basic question: why does any part of Lagos still need a “deal” to get potable water in the first place? The honest answer is that this isn’t a Lekki story at all. It’s a decades-old, citywide one — and Lekki is simply where it’s now most visible.

01Why did the taps go dry in the first place?

The Lagos Water Corporation’s story begins in 1915, when Frederick Lugard, then Governor-General, commissioned the Iju Waterworks. It was built to serve the colonial residents of Ikoyi, distributed through a single 28-inch cast-iron main — enough water for a privileged few, not a city. That original design logic never fully left the system.

A century of under-capacity — key milestones
1915
Iju Waterworks commissioned for colonial Ikoyi
1943
Second trunk main added
1954
Extended to Ikeja, Ikorodu Rd, Ogun River
1967
Lagos State created; inherits Iju Waterworks
1985
Capacity reaches 205 million litres a day
2010
Independent power plant added at Iju
2026
955 million litres a day supply vs 2,455 million demand; Lekki MoU signed

Capacity grew in real but modest steps. What it never did was keep pace with a city that, over the same period, grew into Africa’s most populous metropolis.

11
1915
205
1985
955
2026 (supply)
2,455
2026 (demand)

Figures in million litres a day. Installed capacity for 1915, 1985 and 2026 versus the Lagos Water Corporation’s own estimate of current daily demand (converted from the Corporation’s published gallons-per-day figures).

The corporation has had to publicly apologise for supply disruptions more than once over the years, typically citing technical problems at plants that remain dependent on a national power grid whose own instability compounds everything downstream.

Supply vs demand today
Supply
955m litres/day
Demand
2,455m litres/day
Lagos currently meets well under half of its own estimated daily water demand — a gap that predates Lekki’s development by decades.

Money explains the rest of the gap.

₦10bn
Actual annual budget
(capital + recurrent)
₦300bn
Needed per year
to meet SDG water targets (WaterAid)

Faced with that shortfall, Lagosians simply built their own water system: private boreholes in nearly every compound, sachet and bottled water as a grocery staple rather than a convenience, and an entire informal economy of mairuwa vendors and tanker operators filling the space the utility couldn’t. By the time Lekki emerged as a real estate frontier from the 2000s onward, this parallel private water economy was already the default arrangement most Lagosians lived by.

~35% Share of Lagos households the Lagos Water Corporation can serve, even at full operational capacity

That is what it means to say LSWC lost control of its responsibility decades ago: not that the corporation vanished, but that its share of Lagos’s water supply was ceded, litre by litre and decade by decade, to a private and informal sector that grew precisely because the state couldn’t keep pace.

02What was actually signed

On 9 July 2026, the Lagos State Ministry of the Environment and Water Resources, represented by Commissioner Tokunbo Wahab, signed a one-year MoU with China Harbour Engineering Company (CHEC) and Naston Engineering Nigeria Limited. The agreement took immediate effect. It is a framework for scoping and technical definition — not a construction contract.

The ultimate goal is to improve potable water supply and service delivery for residents.

Tokunbo Wahab, Commissioner for the Environment and Water Resources
The two project lots, at a glance
LotFocusWhat it covers
Lot OneBulk transmissionUnderwater pipeline beneath the Lagos Lagoon into the Lekki Concession Area
Lot TwoDownstream distributionMetering systems and last-mile household/business connections within the concession area

Both lots are expected to result in a concession agreement between Lagos State and the CHEC–Naston consortium, covering detailed engineering, cost estimates and tariff structures.

03The bigger picture this fits into

The Lekki MoU is one strand in a wider, multi-year effort to close that 1,500-million-litre-a-day gap.

Other moving parts

Adiyan II Water Treatment Plant318 million litres a day capacity · 85% complete · to serve 3 million more residents, mostly in western Lagos
Iju/Adiyan rehabilitationTargeting 60% capacity utilisation by August 2026
Mini/micro waterworks rehab5 facilities targeted for completion by November 2026
7-waterworks PPP pilotIncludes a Lekki mini waterworks; 23 bids across 4 lots; 20-year concession tenure; 5% royalty structure

LWC retains full ownership of all water assets.

Helen Omolanke Taiwo, Executive Director, Operations, Lagos Water Corporation

Governor Babajide Sanwo-Olu’s administration has set 2027 as the horizon for the majority of Lagos households to have pipe-borne water. The Lekki MoU is the mechanism by which the fastest-growing, most underserved part of that map gets included in the plan.

04Why the gap between signing and supply matters

An MoU leads to feasibility studies and engineering designs. Those lead to a concession agreement. That agreement leads to financing arrangements, environmental approvals, and — only then — actual excavation under a lagoon in one of the most congested urban environments in Africa. No new water flows into a Lekki tap because of what was signed on 9 July. What changed is that a specific, funded process to get there has now formally started.

05The commentary: who builds Lagos’s water, and on what terms

Seen against that history, the Lekki MoU is easier to place. It isn’t primarily a Lekki-specific fix, and it isn’t really a break from the past either — it’s the latest instalment in a pattern that dates back to when the state government first admitted it couldn’t fund the sector alone: bring in outside capital, hand over the technical and financial heavy lifting, and hope the concession structure delivers what direct public investment couldn’t.

There is also a pattern worth naming about who Lagos increasingly turns to for this: Chinese state-linked engineering firms are now the default partner for large African urban infrastructure — not because of ideology, but because of financing speed and risk appetite that Western multilateral lenders often can’t match on similar timelines.

That isn’t necessarily a problem, but it is a detail worth tracking rather than skipping over. The eventual concession agreement will set tariff structures and — following the pattern already set by the mini-waterworks PPP pilot — likely a fixed 20-year term with royalty conditions. Those numbers, not the signing ceremony, will determine what a Lekki household actually pays for water that used to come from a borehole or a tanker.

06What to watch next

  • Publication of the technical studies and cost estimates the consortium is contracted to deliver
  • Timeline and terms of the eventual concession agreement, particularly the tariff structure
  • Whether last-mile connection costs fall on the concessionaire, government, or households
  • Any public consultation before metering begins in Lekki
  • Progress on Adiyan II and Iju/Adiyan rehabilitation, since Lekki’s bulk supply depends on upstream treatment capacity existing at all

The bottom line

An underwater pipeline is a genuinely difficult engineering problem, and Lekki’s water crisis has been overdue for a fix for a decade. But it would be a mistake to read this MoU as a Lekki story with a Lekki solution. It is one more chapter in Lagos State’s century-long struggle to fund a water system built for a colonial outpost and never fully rebuilt for a megacity. This MoU is a real, necessary step — but it’s the first of several, and the distance between “MoU signed” and “water running” in Lagos has usually been measured in years, not months. For now, keep the tanker driver’s number saved — in Lekki, and everywhere else in Lagos too.

Lagos Water Corporation Lekki Water Infrastructure Tokunbo Wahab China Harbour Engineering PPP Lagos State